Report on Code Compliance - Quick Pole Line Design Software Yes
Summary by Section Yes Partial No N/A Total Clauses No
I. General Provisions 0 0 0 9 9 Partial
 II. Definition of Terms 0 0 0 1 1 N/A
III. Requirements for All Lines 2 2 3 2 9
IV. Strength Requirements 7 1 0 2 10
V. Detailed Construction Requirements for Supply Lines 1 2 3 4 10
VI. Detailed Construction Requirements for Tower Lines 2 0 1 3 6
VII. Detailed Construction Requirements for Trolley 1 2 5 2 10
VIII. Detailed Construction Requirements for Communication Lines 3 3 3 1 10
 IX. Joint Poles or Poles Jointly Used 1 1 2 1 5
X Supply and Communication Lines in Line Crossings or Conflicts 0 2 3 1 6
XI. Supply Lines or Communication Lines Crossing Over Railroads 0 0 0 0 0
Total 17 13 20 26 76
34% 26% 40%
STATE OF CALIFORNIA GENERAL ORDER No. 95 Compliant ? Notes / Proof 50
11 Purpose of rules N/A 0 0 0 1
12 Applicability of rules N/A 0 0 0 1
13 Scope of rules N/A 0 0 0 1
14 Limiting Conditions Specified N/A 0 0 0 1
15 Exemptions or Modifications N/A 0 0 0 1
16 Saving Clause N/A 0 0 0 1
17 Investigation of Accidents N/A 0 0 0 1
18 Reporting and Resulution of Safety Hazards N/A 0 0 0 1
19 Cooperation with Commission Staff N/A 0 0 0 1
20 - 24 Definitions N/A 0 0 0 1
31 Application N/A 0 0 0 1
32 General Arrangement of Lines No Inter-circuit and crossing separation requirements not enforced 0 0 1 0
33 Grounds and Neutrals No While supported in principle, the designer is responsible. 0 0 1 0
34 Foreign Attachments Partial Most, but not all technical requirements can be addressed with Quick Pole 0 1 0 0
35 Vegetation Management No 0 0 1 0
36 Pole Clearances from Railroad Tracks No 0 0 1 0
37 Minimum Clearances of Wires above Railroads, Thoroughfares,
Buildings, Etc.
Partial Vertical clearances in cases 1-5,11,12 are enforced 0 1 0 0
38 Minimum Clearances of Wires from Other Wires Partial Vertical separation between supply and communication is enforced. 0 1 0 0
39 Minimum Clearances of Wires from Signs No 0 0 1 0
40 Strength requirements - General N/A 0 0 0 1
41 Classification of Circuits and Grades of Construction N/A 0 0 0 1
42 Grades of Construction Yes User to select the appropriate grade of construction 1 0 0 0
43 Temperature and Loading Yes User selects appropriate Load Case (Heavy or Light) 1 0 0 0
44 Safety Factors Yes 1 0 0 0
45 Transverse Strength Requirements Yes 1 0 0 0
46 Vertical Strength Requirements Yes 1 0 0 0
47 Longitudinal Strength Requirements Partial User is required to add Longitudinal loads as Point Loads 0 1 0 0
48 Strength of Materials Yes 1 0 0 0
49 Detailed Strength Requirements Yes Minimum conductor sizes not enforced. 1 0 0 0
50 Detailed Construction Requirements for Supply Lines - General N/A 0 0 0 1
51 Poles, Towers and Structures N/A 0 0 0 1
52 Crossarms N/A 0 0 0 1
53 Pins, Deadends, Conductor Suspensions and Fastenings N/A 0 0 0 1
54 Conductors Partial Swimming pool scenarios need to be considered by the designer. Between conductor and other object distances not assessed. Climbing space considerations not evaluated. 0 1 0 0
55 Conductor Insulators No 0 0 1 0
56 Overhead Guys, Anchor Guys and Span Wires Partial Radial/horizontal distance requirements not evaluated. Guy insulator locations and voltage ratings not tested. 0 1 0 0
57 Messengers and Insulated Cables Yes Where messengers and supply are on the same crossarm (rare), designer must consider requirements themselves. 1 0 0 0
58 Miscellaneous Equipment No 0 0 1 0
59 Common Primary and Secondary Grounded Neutral Systems No 0 0 1 0
60 Detailed Construction Requirements for Tower Lines
and Extra High Voltage Lines - General
N/A 0 0 0 1
61 Towers N/A Material minimum size requirements not considered. 0 0 0 1
63 Deadends, Conductor Suspensions and Fastenings N/A 0 0 0 1
64 Conductors Yes 1 0 0 0
65 Conductor Insulators No 0 0 1 0
66 Guys Yes 1 0 0 0
70 Detailed Construction Requirements for Trolley and Electric
Railway Contact and Feeder Conductors and Their
Supporting Messengers, Span Wires, Etc.-General
N/A 0 0 0 1
71 Poles, Towers and Structures Partial Horizontal clearances from rails not evaluated 0 1 0 0
72 Crossarms No 0 0 1 0
73 Pins, Deadends and Conductor Fastenings No 0 0 1 0
74 Conductors Partial Minimum trolley wire sizes and horizontal distances to other conductors/objects not enforced. 0 1 0 0
75 Conductor Insulators No 0 0 1 0
76 Guys and Anchors Yes 1 0 0 0
77 Span Wires, Backbones, Messengers, Etc No 0 0 1 0
78 Attachments of Feeder, Communication or Foreign Conductors No 0 0 1 0
79 Third Rails N/A 0 0 0 1
80 Detailed Construction Requirements for Communication
Lines-General
N/A 0 0 0 1
81 Poles, Towers and Structures Partial Horizontal clearances from rails not evaluated 0 1 0 0
82 Crossarms Partial Excludes inspection requirements 0 1 0 0
83 Pins, Deadends and Conductor Fastenings No Bonding requirements not enforced 0 0 1 0
84 Conductors Yes Except swimming pool, horizontal and crossing clearances; plus climbing space considerations 1 0 0 0
85 Conductor Insulators No 0 0 1 0
86 Guys Yes Guy insulator locations and voltage ratings not tested. 1 0 0 0
87 Cables and Messengers Yes Except fibre optic cable transitions and crossarm horizontal spacing requirements 1 0 0 0
88 Miscellaneous Equipment Partial Maximum size requirements within the climbing space is not enforced 0 1 0 0
89 Private Communication Circuits No Treated as regular communication facilities 0 0 1 0
90 Joint Poles or Poles Jointly Used - General N/A 0 0 0 1
91 Poles, Towers and Structures Yes No support for pole steps 1 0 0 0
92 Conductors, Cables and Messengers Partial No support for supply circuits below communication. Vertical spacing of communication circuits attached to pole is not enforced. Grounding of communication is not tested. 0 1 0 0
93 Climbing Space No 0 0 1 0
94 Antennas No 0 0 1 0
100 Supply and Communication Lines in Line Crossings or
Conflicts - General
N/A 0 0 0 1
101 Poles, Towers and Structures Partial Hardware is not tested for uplift capacity due to elevation changes 0 1 0 0
102 Pins and Conductor Fastenings No 0 0 1 0
103 Conductors Partial Conductor splices are not known to Quick Pole. Insulator pin bonding requirements are not considered. Minimum communication wire sizes not enforced. 0 1 0 0
104 Insulators for Supply Conductors No 0 0 1 0
105 Screens and Cradles No 0 0 1 0
110 Supply Lines or Communication Lines Crossing over
Railroads - General
N/A 0 0 0 1
111 Poles, Towers and Structures Partial Horizontal clearances from rails not evaluated. Uplift on crossing poles not evaluated against hardware capacity 0 1 0 0
112 Pins And Conductor Fastenings No 0 0 1 0
113 Conductors No Conductor splices are not known to Quick Pole. Insulator pin bonding requirements are not considered. Minimum communication wire sizes not enforced. 0 0 1 0
114 Grounded Insulator Pins No 0 0 1 0
115 Screens and Cradles No 0 0 1 0